From Container to First FRP Sheet: An Installation and Commissioning Checklist

Nov 18,2026

From Container to First FRP Sheet: An Installation and Commissioning Checklist

 

The machine usually takes about 60 days from the factory to arrive at the customer's factory (this also depends on the distance from the customer's country to China and the mode of transportation). Before the machine arrives, DNUO Company usually asks the customer to prepare the raw materials needed for production in advance: resin + film + glass fiber, etc. After frp sheet machine arrives, the machine engineer will set off to the customer's factory. We guarantee that the installation will be arranged immediately after the machine arrives.
The first step for the engineer at the factory: preparing the site. The engineer checks the ground load-bearing and levelness, the machine area and lifting passage, power capacity and voltage system, compressed air, ventilation and exhaust, as well as the stable resin storage area. These are the tasks that the engineer checks first, and they seem simple, but they play an important role in the subsequent work.

The second step - unloading, unpacking, positioning. The engineer will check each part of the machine item by item and check if the machine components are damaged during transportation. Then, he will move each section of the machine to the position and align it.


The third step - assembly, wiring, calibration. The engineer will perform mechanical assembly and electrical wiring. This step is the most time-consuming part of the entire frp panel making machine installation process. This process will ensure the complete installation of the machine and its ability to operate.
The fourth step - no-load test and safety test. After the fiberglass sheet machine is installed, it will be prioritized to run without load to observe if there are any jams, abnormal sounds, etc. The safety performance of the machine will also be tested.
The fifth step - trial production. Trial production is to match the resin flow rate, the thickness of the sheet, the yarn ratio, and the production speed of the machine with the temperature of the heating box. Several rounds of adjustments need to be prepared. The goal is to produce consistent high-quality sheets. The adjusted parameters will be recorded and saved in the control system, which will be the subsequent production standard.


The sixth step - training, continuous operation, and acceptance. The engineer will provide training to the operators and maintenance personnel. The engineer will conduct specific training based on the actual production situation and the specific requirements of the local market for the sheets. At the same time, the operators will perform practical operations. Based on their practical operations, the engineer will provide guidance. The engineer will confirm that the FRP sheet production line is running stably and that the operators are operating correctly before leaving the factory.


The five things that most often cause production delays: mismatch of power supply and machine, foundation not reaching the maintenance period, raw materials still being held up in customs clearance, language barriers turning a two-hour task into a two-day one, and missing spare parts. These five things can all be avoided in the planning stage.
FRP panel machine training is completed on-site. Instead of troubleshooting after problems occur, we prefer to provide the list to you before the machine is shipped. Request the installation preparation list and send us the factory floor plan, power conditions, and target products. We will mark the areas that need to be modified.